Start Date:

02/07/2020 4:35 PM

End Date:

04/30/2020 11:59 PM

Description:

Effective Sunday, February 9, 2020, and continuing through late April 2020, LocalLink 83 northbound and LocalLink 92 southbound service will be diverted due to the Baltimore Gas and Electric Reisterstown Road MD 140 Electric Reliability Upgrade Project. During the first phase of this project, Reisterstown Road near Old Court Road will have a change in the traffic pattern, whereas no left turns will be permitted from Reisterstown Road, northbound or southbound, onto Old Court Road, eastbound or westbound. This construction will necessitate the following temporary diversions:


LocalLink 83

Northbound: Via the regular route northbound on Reisterstown Road to Old Court Road, then:
Straight on Reisterstown Road
Left on Naylors Lane
Right on Old Court Road, then via the regular route.

Southbound: No Change.


LocalLink 89

Northbound and When Southbound: No Change.


LocalLink 92

Northbound: No Change

Southbound: Via the regular route southbound on Reisterstown Road and Hooks Lane, then:
Left on Hooks Lane
Right on Park Heights Avenue
Left on Old Court Road, then via the regular southbound route.

Affected Routes:

  • 83: MONDAWMIN - OLD COURT METRO
  • 89: ROGERS AVE - OWINGS MILLS
  • 92: GLEN - BAAS & TALMUDICAL

Cause:

Construction

Effect:

Detour